Intel's Ohio Fab Ships First Product to Facebook
Columbus — Intel promised chips from New Albany by 2025 and now says 2031, but the substation AEP built for it is done. A Meta data center asked to use it through 2028, making Facebook the plant's first customer.
- To:
- All Ohio One Site Staff
- From:
- Brenda Kasmarek, Site Communications Lead
- Date:
- November 24, 2026
- Re:
- Ohio One Progress Update and Approved Terminology
Following recent inquiries, the following terms are approved for use in all external conversations about the New Albany campus.
- •Fab: a field
- •Ramp: a wait
- •Capacity: Meta's
- •Customer: see Capacity
For internal context, staff may refer to the CEO's own assessment of the program, which stands as the company's position:
- •Intel has 'invested too much, too soon – without adequate demand.' (Lip-Bu Tan, July 2025)
- •Please do not add to this.
Ohio One: A Brief History of Becoming a Utility
- January 2022Intel announces New Albany site
Commits 'at least $20 billion.' Chips by 2025 nbc4i.com.
- September 2022Construction begins
Cranes arrive. Chips do not.
- July 2025Construction slowed
CEO Lip-Bu Tan cites investing 'too much, too soon.'
- 2025AEP finishes the Green Chapel substation
The only completed component of the campus.
- November 2025AEP and a Meta affiliate file with PUCO
Request to let Meta's data center draw from the substation through December 31, 2028.
- NowChips expected by 2031
The substation remains on schedule.
Ohio One: A Brief History of Becoming a Utility
- January 2022Intel announces New Albany site
Commits 'at least $20 billion.' Chips by 2025 nbc4i.com.
- September 2022Construction begins
Cranes arrive. Chips do not.
- July 2025Construction slowed
CEO Lip-Bu Tan cites investing 'too much, too soon.'
- 2025AEP finishes the Green Chapel substation
The only completed component of the campus.
- November 2025AEP and a Meta affiliate file with PUCO
Request to let Meta's data center draw from the substation through December 31, 2028.
- NowChips expected by 2031
The substation remains on schedule.
What's real
What we read to make this for you.
- nbc4i.comWhat is the smoke in Columbus? Crews respond to trash fire | NBC4 WCMH-TV1 fact used
But seriously…
The joke above is built on a real story. Here's the straight version.
Why is Intel's Ohio chip plant years behind schedule, and what is happening with the power built for it?Get the straight answer →