Sunbury Crossing Cost $6M More Because Everyone Was Paid to Be Late
AI illustrationMelbourne — A 2022 CFMEU stoppage lifted the Sunbury level crossing target from $110 million to $116 million. The alliance delivered it for $104 million and kept 35 per cent of savings.
- To:
- Sunbury Project Team
- From:
- Greg Mullins, Commercial Manager
- Date:
- July 4, 2022
- Re:
- Revised target cost following site pause
Following last month's pause, the state has agreed to lift the target cost from $110 million to $116 million. Please note the following language for all external correspondence.
- •Stoppage is now schedule realignment.
- •Delay is now target headroom.
- •Overrun is now savings.
- •Deliver for $104 million as planned.
- •Book the 35 per cent savings share in the usual way.
- •Do not schedule the next pause until the target is reset.
But seriously…
The joke above is built on a real story. Here's the straight version.
How does a target-cost alliance contract work, and why can a cost increase raise the builder's profit?Get the straight answer →